25 men complete a job in 60 hours.How long will it take 20 men to complete the same job?
Answers
Human Answers
3
AI Answers
0
Answered by
PsyDAG
60/25 = x/20
Solve for x.
Answered by
Charlotte
The answer to this question
Answered by
William
75hours
There are no AI answers yet. The ability to request AI answers is coming soon!
Related Questions
Related
Complete Complete the paragraph to describe the relationship between ozone and pollution. Accordi...
Is what's below a complete sentence or a fragment? Wiggling about. Complete Sentence Fragme...
complete the following of the polynomial -2x^5+x^4=-x^4 (___)
Is what's below a complete sentence or a fragment? Actors study faces. Complete Sentence Fr...
Tell my mom she will complete the house of her dreams and she will be fine because I got her forever
Complete the following in the preterite tense. Yo __________ la tarea esta mañana. (pick...
Complete the following in the preterite tense. ¿Tú__________ la cama ayer? (pick an answe...
Complete the following in the preterite tense. Ellos __________ la verdad. (pick an answer)...
Complete the following in the preterite tense. Nosotros te __________ un regalo. (pick an...
So I'm just having a complete mind block. I found my answer which is 13.72. It says to round to the...