1285 hrs to manufacture first unit - expects to achieve a 92% unit learning curve - how many hours would be required to manufacture units 51-100
Ask a New Question
or
answer this question
.
Similar Questions
1) It took a contractor 1285 hours to manufacture their first unit of an item. If the contractor expects to achieve a 92% unit
4 answers
It took a contractor 1285 hours to manufacture their first unit of an item. If the contractor expects to acheive a 92% unit
0 answers
it cost a contactor $13750 to manufacture their first unit. The company expects to experience a 93% unit learning curve.
1 answer
a manager is trying to estimate the appropriate learning curve for a certain job. the manager notes that the first four units
0 answers
more similar questions