A mechanic can do a job in 2hr. It takes his assistant 3hr to do the same job how long would it take them to complet the job if they worked together?
10 years ago

Answers

Reiny
mechanic' rate --- 1/2
assistant's rate --- 1/3
combined rate = 1/2 + 1/3 = 5/6

time at combined rate = 1/(5/6)
= 6/5 hrs
or 1 hour 20 minutes
10 years ago
Reiny
oops, 1/5 hr = 12 minutes, not 20 minutes

so 1 hour, 12 minutes
10 years ago

Related Questions

A mechanic pushes a 2.50 x 10^3 kg car from the rest to a speed of v, doing 5000J of work in the pro... A mechanic pushes a 2.0 103 kg car from rest to a speed of v, doing 5350 J of work in the process.... A mechanic pushes a 2,500 kg car from rest to a speed v, with 5000J of work. During this process the... A mechanic is working on a car that has a 10 Liter radiator that is currently filled with a mixture... A mechanic pushes a 2.20 103-kg car from rest to a speed of v, doing 4,550 J of work in the process... if thr mechanic says that it will take seven days to repair your car, then it will actually take ten... a mechanic is looking over his supply of oil. he counted a jug that had 2 quarts of oil another had... A mechanic wants Then mechanic said the car needed some brake things replaced, which words can replace the in precise...
Ask a New Question
Archives Contact Us Privacy Policy Terms of Use