A company manufactures x units of Product A and y units of Product B, on two machines, I and II. It has been determined that the company will realize a profit of $3/unit of Product A and a profit of $6/unit of Product B. To manufacture a unit of Product A requires 6 min on Machine I and 5 min on Machine II. To manufacture a unit of Product B requires 9 min on Machine I and 4 min on Machine II. There are 5 hr of machine time available on Machine I and 3 hr of machine time available on Machine II in each work shift. How many units of each product should be produced in each shift to maximize the company's profit?
(x,y)=?
What is the maximum return?
(x,y)=?
What is the maximum return?
Answers
Answered by
Steve
maximize p=3x+6y subject to
6x+9y <= 300
5x+4y <= 180
Now just draw the lines and find the vertices. There are many helpful online sites to verify your work. One is at
http://www.zweigmedia.com/RealWorld/LPGrapher/lpg.html
6x+9y <= 300
5x+4y <= 180
Now just draw the lines and find the vertices. There are many helpful online sites to verify your work. One is at
http://www.zweigmedia.com/RealWorld/LPGrapher/lpg.html
There are no AI answers yet. The ability to request AI answers is coming soon!
Submit Your Answer
We prioritize human answers over AI answers.
If you are human, and you can answer this question, please submit your answer.