Asked by Anonymous
The time required to complete a project is known to be normally distributed with a mean of 44 weeks and a standard deviation of 8 weeks.
(a) What is the probability that the project is finished in 40 weeks or fewer?
(a) What is the probability that the project is finished in 40 weeks or fewer?