The time required to complete a project is known to be normally distributed with a mean of 44 weeks and a standard deviation of 8 weeks.
(a) What is the probability that the project is finished in 40 weeks or fewer?

Answers

Answered by Reiny
enter your data into
http://davidmlane.com/hyperstat/z_table.html

click on "below" and enter 40
Answered by Anonymous
40